Domains
Agile Management
Master Agile methodologies for efficient and timely project delivery.
View All Agile Management Coursesicon-refresh-cwCertifications
Scrum Alliance
16 Hours
Best Seller
Certified ScrumMaster (CSM) CertificationScrum Alliance
16 Hours
Best Seller
Certified Scrum Product Owner (CSPO) CertificationScaled Agile
16 Hours
Trending
Leading SAFe 6.0 CertificationScrum.org
16 Hours
Professional Scrum Master (PSM) CertificationScaled Agile
16 Hours
SAFe 6.0 Scrum Master (SSM) CertificationAdvanced Certifications
Scaled Agile, Inc.
32 Hours
Recommended
Implementing SAFe 6.0 (SPC) CertificationScaled Agile, Inc.
24 Hours
SAFe 6.0 Release Train Engineer (RTE) CertificationScaled Agile, Inc.
16 Hours
Trending
SAFe® 6.0 Product Owner/Product Manager (POPM)IC Agile
24 Hours
ICP Agile Certified Coaching (ICP-ACC)Scrum.org
16 Hours
Professional Scrum Product Owner I (PSPO I) TrainingMasters
32 Hours
Trending
Agile Management Master's Program32 Hours
Agile Excellence Master's ProgramOn-Demand Courses
Agile and ScrumRoles
Scrum MasterTech Courses and Bootcamps
Full Stack Developer BootcampAccreditation Bodies
Scrum AllianceTop Resources
Scrum TutorialProject Management
Gain expert skills to lead projects to success and timely completion.
View All Project Management Coursesicon-standCertifications
PMI
36 Hours
Best Seller
Project Management Professional (PMP) CertificationAxelos
32 Hours
PRINCE2 Foundation & Practitioner CertificationAxelos
16 Hours
PRINCE2 Foundation CertificationAxelos
16 Hours
PRINCE2 Practitioner CertificationSkills
Change ManagementMasters
Job Oriented
45 Hours
Trending
Project Management Master's ProgramUniversity Programs
45 Hours
Trending
Project Management Master's ProgramOn-Demand Courses
PRINCE2 Practitioner CourseRoles
Project ManagerAccreditation Bodies
PMITop Resources
Theories of MotivationCloud Computing
Learn to harness the cloud to deliver computing resources efficiently.
View All Cloud Computing Coursesicon-cloud-snowingCertifications
AWS
32 Hours
Best Seller
AWS Certified Solutions Architect - AssociateAWS
32 Hours
AWS Cloud Practitioner CertificationAWS
24 Hours
AWS DevOps CertificationMicrosoft
16 Hours
Azure Fundamentals CertificationMicrosoft
24 Hours
Best Seller
Azure Administrator CertificationMicrosoft
45 Hours
Recommended
Azure Data Engineer CertificationMicrosoft
32 Hours
Azure Solution Architect CertificationMicrosoft
40 Hours
Azure DevOps CertificationAWS
24 Hours
Systems Operations on AWS Certification TrainingAWS
24 Hours
Developing on AWSMasters
Job Oriented
48 Hours
New
AWS Cloud Architect Masters ProgramBootcamps
Career Kickstarter
100 Hours
Trending
Cloud Engineer BootcampRoles
Cloud EngineerOn-Demand Courses
AWS Certified Developer Associate - Complete GuideAuthorized Partners of
AWSTop Resources
Scrum TutorialIT Service Management
Understand how to plan, design, and optimize IT services efficiently.
View All DevOps Coursesicon-git-commitCertifications
Axelos
16 Hours
Best Seller
ITIL 4 Foundation CertificationAxelos
16 Hours
ITIL Practitioner CertificationPeopleCert
16 Hours
ISO 14001 Foundation CertificationPeopleCert
16 Hours
ISO 20000 CertificationPeopleCert
24 Hours
ISO 27000 Foundation CertificationAxelos
24 Hours
ITIL 4 Specialist: Create, Deliver and Support TrainingAxelos
24 Hours
ITIL 4 Specialist: Drive Stakeholder Value TrainingAxelos
16 Hours
ITIL 4 Strategist Direct, Plan and Improve TrainingOn-Demand Courses
ITIL 4 Specialist: Create, Deliver and Support ExamTop Resources
ITIL Practice TestData Science
Unlock valuable insights from data with advanced analytics.
View All Data Science Coursesicon-dataBootcamps
Job Oriented
6 Months
Trending
Data Science BootcampJob Oriented
289 Hours
Data Engineer BootcampJob Oriented
6 Months
Data Analyst BootcampJob Oriented
288 Hours
New
AI Engineer BootcampSkills
Data Science with PythonRoles
Data ScientistOn-Demand Courses
Data Analysis Using ExcelTop Resources
Machine Learning TutorialDevOps
Automate and streamline the delivery of products and services.
View All DevOps Coursesicon-terminal-squareCertifications
DevOps Institute
16 Hours
Best Seller
DevOps Foundation CertificationCNCF
32 Hours
New
Certified Kubernetes AdministratorDevops Institute
16 Hours
Devops LeaderSkills
KubernetesRoles
DevOps EngineerOn-Demand Courses
CI/CD with Jenkins XGlobal Accreditations
DevOps InstituteTop Resources
Top DevOps ProjectsBI And Visualization
Understand how to transform data into actionable, measurable insights.
View All BI And Visualization Coursesicon-microscopeBI and Visualization Tools
Certification
24 Hours
Recommended
Tableau CertificationCertification
24 Hours
Data Visualization with Tableau CertificationMicrosoft
24 Hours
Best Seller
Microsoft Power BI CertificationTIBCO
36 Hours
TIBCO Spotfire TrainingCertification
30 Hours
Data Visualization with QlikView CertificationCertification
16 Hours
Sisense BI CertificationOn-Demand Courses
Data Visualization Using Tableau TrainingTop Resources
Python Data Viz LibsCyber Security
Understand how to protect data and systems from threats or disasters.
View All Cyber Security Coursesicon-refresh-cwCertifications
EC-Council
40 Hours
Certified Ethical Hacker (CEH v12) CertificationISACA
22 Hours
Certified Information Systems Auditor (CISA) CertificationISACA
40 Hours
Certified Information Security Manager (CISM) Certification(ISC)²
40 Hours
Certified Information Systems Security Professional (CISSP)(ISC)²
40 Hours
Certified Cloud Security Professional (CCSP) Certification16 Hours
Certified Information Privacy Professional - Europe (CIPP-E) CertificationISACA
16 Hours
COBIT5 Foundation16 Hours
Payment Card Industry Security Standards (PCI-DSS) CertificationOn-Demand Courses
CISSPTop Resources
Laptops for IT SecurityWeb Development
Learn to create user-friendly, fast, and dynamic web applications.
View All Web Development Coursesicon-codeBootcamps
Career Kickstarter
6 Months
Best Seller
Full-Stack Developer BootcampJob Oriented
3 Months
Best Seller
UI/UX Design BootcampEnterprise Recommended
6 Months
Java Full Stack Developer BootcampCareer Kickstarter
490+ Hours
Front-End Development BootcampCareer Accelerator
4 Months
Backend Development Bootcamp (Node JS)Skills
ReactOn-Demand Courses
Angular TrainingTop Resources
Top HTML ProjectsBlockchain
Understand how transactions and databases work in blockchain technology.
View All Blockchain Coursesicon-stop-squareBlockchain Certifications
40 Hours
Blockchain Professional Certification32 Hours
Blockchain Solutions Architect Certification32 Hours
Blockchain Security Engineer Certification24 Hours
Blockchain Quality Engineer Certification5+ Hours
Blockchain 101 CertificationOn-Demand Courses
NFT Essentials 101: A Beginner's GuideTop Resources
Blockchain Interview QsProgramming
Learn to code efficiently and design software that solves problems.
View All Programming Coursesicon-codeSkills
Python CertificationInterview Prep
Career Accelerator
3 Months
Software Engineer Interview PrepOn-Demand Courses
Data Structures and Algorithms with JavaScriptTop Resources
Python TutorialThere are two ways of Sprint Planning:
Velocity-based planning of the Sprint determines how much work the team can accomplish in the Sprint. In any Sprint, the velocity is calculated as the number of Story points completed per sprint. This is a basic introduction to Velocity-based Sprint planning. We will learn more about this type of sprint planning in the next section.
Capacity-based sprint planning, also called Commitment-based Sprint planning, is based on the team’s available capacity (in hours) for the sprint and tries to fill that capacity effectively without overburdening and undercommitting the team members. Capacity-based planning is considered the best way of sprint planning due to the following 3 main reasons.
In capacity-based sprint planning, a team commits to one product backlog item at a time by roughly estimating the involved tasks and finishing the task when they feel that the Sprint is full.
While planning a capacity-based sprint, it is crucial that the team’s commitment is not looked at as a guarantee. Here, commitment can be viewed as a team’s commitment to do its best. In fact, teams can perform at their highest level 80% of the time. The commitment should be something that can be taken seriously and should utilize most of the time. In this way, businesses gain confidence in what time they can deliver the products.
A capacity or commitment-driven sprint planning meeting involves the Scrum Master, Product Owner, and all the development team members. The Product Owner presents the highest-priority product backlog items in the meeting and introduces those top-priority items to the team.
Scrum teams often face the challenges of sprint commitments during sprint planning. The challenges include:
The second challenge is a crucial one because to commit to the sprint goal, you need to know the capacity of the current team, and the capacity can be calculated as per the team members’ availability in the sprint.
Let’s understand it with an example:
Consider a team consisting of 6 people working for 8 hours per day for 3-week sprint (15 days). Then the total capacity of the team can be calculated as:
Team’s Capacity = number of team members * time in hours * days
= 6*8*15
= 720 hours
But planning a total capacity in this pattern may:
Then how to decide the capacity that the team can commit to? And how the team can make the sprint planning events more effective? Focus Factor (F.F) can be used to get the real capacity.
This focus factor lies in the range of 0.6 - 0.8.
Project Managers generally plan for 6-6.5 hours per day for executing a project. So, the focus factor is nothing but the capability of the teams to stay focused on the sprint goals without any impediments. You can get the ‘real capacity’ when you multiply the total capacity with a focus factor. E.g. Consider, focus factor is 0.6, then the real capacity of the team will be 720 * 0.6 = 432 hours.
The team can utilize these 432 hours of work in the present sprint. The team selects the highest-priority items declared by the Product Owner and divide those stories into tasks to estimate each task for hours. So, the team will pick up the stories until the time length does not exceed more than 432 hours (as per this example).

Using less focus factor, if the team members have ended up the current sprint with all the work items (tasks), they can add more tasks in that sprint. Teams can retrospect on this to check for raising the focus factor to reach a sustainable flow. Going above 0.8 can be risky and can slow down the teams too.
In case of chaotic organizations, the focus factor usually remains on the extreme left, such as 0.6 or below. The chaotic organizations show no rhythm in working. Such organizations represent factors like unplanned meetings, recruitment HR bringing someone for an interview, pre-sales emergency, not having predetermined working hours, less clarity on sprint backlog items, cluttered team structures, and so on.
Note: It is recommended to use less Focus Factor (say 0.6), if:
Sprint Backlog is the output of the Capacity-based Sprint Planning meeting. A Sprint Backlog is nothing, but a list of the product backlog items that the team commits to deliver, plus a list of tasks needed to deliver those product backlog items. Also, each task on the Sprint backlog is usually estimated.