For enquiries call:
+1-469-442-0620
HomeBlogProject ManagementAn Essential Guide To PRINCE2 Documents
PRINCE2 is a methodology for project management that outlines a series of project management documents called products that assist project managers in performing their responsibilities. The PRINCE2 certification course processes and themes are mapped to the documents that are used to accomplish each process. They are regarded as the methodology's core components.
The diagram below titled "The PRINCE2 Product Map" will help us approach project initiation documentation PRINCE2.
As you can see, if you look at the previous diagram, the highest level in the project is Corporate or Programme Management, or the Customer (CPC). Following the Project Board who directs the project. Next, there is the Project Manager, who manages the project, and then there is the Team, who actually does the work and develops the products. Therefore, we have various project labels divided into layers:
Furthermore, we have several stages which comprise the vertical lines, namely:
The PRINCE2 documents templates created during the preproposal stage are the first ones to discuss. During this stage, the leftmost vertical line on the diagram represents the contents.
A Project Mandate is created by the CPC prior to the start of the project, and you will note that this comes from outside the project and is done before the "Starting up a Project Process" phase.
Next, we have the Outline Business Case, which is displayed above the gray line between the Project Manager and Project Board. A member of the Project Board should be responsible for writing this document. In more detail, the Executive is the one who is responsible for this document.
In the diagram below, you can see that project managers are responsible for all other documents from the Starting Up a Project Process.
You will find the following documents here
During the Pre-Project Stage, you will only create these documents. Next, we will discuss the Initiation Stage, which is the first step of the process.
Project Manager Layer
The first thing we see is the Business Case, which has been moved since the project manager updated the document. Project Managers might start the process in the Pre-Project phase and then add extra cost information, and that would be looked at by Executives as well.
In terms of Project Initiation Documentation (PID), we have the following documents
Below are some documents that are not included in the PID process
This is the last stage of the Stage Boundary process, in which the next stage will be planned.
The Project Manager Layer involves
A decision to proceed with the project is made based on the PID documents (Project Board) exposed above. In the event that they agree to move forward with the project, the project manager will start by completing the Controlling a Stage Process. He/she must write the following documents:
The following documents need to be updated:
In the end, the Project Manager must create a set of Work Packages for the Project Team to implement.
The Team Manager Layer consists of:
Upon delivering all the Work Packages to the Team Manager, the following documents must be created
The layer of Project Managers
As part of the stage boundary process, the Project Manager created the following documents
The following documents must also be updated
The layer of the Project Manager
The Project Manager must create the following documents at the end of the project
After updating these documents, the PM moves on to the next
PRINCE2 foundation training course equips you with minute details of the PRINCE2 Documents and more.
These are the documents that comprise project documents.
Projects are undertaken because of their benefits. Their value represents what the project is trying to accomplish. As projects produce products or services, those products are intended to be beneficial to the parent organization. Benefits management must outline how the benefits will be realized to the parent organization even if the product is great. The project is still a failure if the benefits are not realized. A management plan is necessary to achieve those benefits and measures how to measure them.
Identifying the business fundamentals that underlie the project is described within the business case. The document identifies the reasons for undertaking the project, the expected return on investment, and the expected benefits. This document presents several business scenarios and their financial analyses.
During the initiation of a project, the approach identifies policies and procedures that are applicable. Any change in the project plan, such as a change in budget, schedule, scope, etc., can be considered a change in scope. A report detailing the reports that will be produced should a project change occur, along with who will be responsible for approving this report.
A team manager is responsible for producing some or all of the project's deliverables, so he or she creates this report, but the project manager is its primary audience. As needed, the project manager is updated by the team manager on progress on the project. Checkpoint reports may take any form, from verbal updates to formal reports.
A communication management approach explains how the project will communicate with its stakeholders. Each stakeholder will have a different need for communication, whether these needs are positive or negative. A communications management approach identifies the type of communication, its frequency, mode of delivery, intended audience, and any other items that are necessary to establish a solid project management foundation for communication.
Projects need a tracking mechanism when developing new products or services, both to avoid confusion and to keep track of their progress. The configuration item record contains information such as the version number, the current status, the location, and the person responsible.
Besides formal logs, project managers record informal items, action items, and other issues not detailed in the logs. They serve as an electronic project diary. Additionally, if neither of those has been established, it can also be used as an issue and risk register.
This report documents the project's completion. A final report includes information regarding final details, final details, and final costs.
Obtaining formal approval from the project board to proceed to the next stage requires producing this report by the project manager. Besides reviewing the project's business case, a review of the completion stage, and any major risks, the report includes a discussion of any issues that might arise. A quality control analysis is carried out on the deliverables and approval records. On the basis of the current stage's experience, the project manager forecasts the next stage's management.
A management stage produces an exception report when it exceeds its tolerances in a particular area. In the report, the project board is given a number of options to address the problem and one is recommended. It is also discussed how the decision will impact the business case. A stage plan for that management stage must be replaced by the exception plan when the project is experiencing an exception. Once approved by the project board, the exception plan becomes the new stage plan.
The project manager prepares a highlight report to provide an update on the project status to the project board. As part of the project initiation process, the project board determines the intervals for preparing highlight reports. The report includes detailed information about the budget, schedule, scope, risks, and benefits. In it, the following reporting period is summarized, and a forecast is given for the upcoming period. As well as highlighting any issues that have arisen, the report outlines what will be done about them.
An issue is any problem that occurs, regardless of whether it puts the project out of tolerance. Logging and tracking issues help ensure that they are handled promptly and decisively. It allows a project to document what issues were encountered during its life-cycle and provides lessons learned which can be applied to future projects.
A formal issue report is not required for all issues, but when formal changes are needed to resolve an issue, a formal report is produced that includes a description, impact assessment, and recommendations for change. A living document, the issue report is updated as the assessment or decision is made about the issue.
Lessons learned from this log can be applied to future projects within the organization, or to the remainder of the project.
Lessons reports are useful when lessons learned are complex, or require action within a short time frame. Additionally, they can be used to communicate improvements to stakeholders, the parent organization, or the project team.
All the information necessary to communicate how the project intends to accomplish its goals can be found in the project plan. A schedule, budget, scope statement, benefits analysis, risk analysis, and delivery method are included. Generally, project plans are organized into three categories the main project plan, the stage plan, and the team plan.
The project manager produces the first two, while the team manager produces the third. The project plan and stage plans are quite similar in content, but the stage plan addresses a short portion of the project. They identify the work packages (work breakdown structure) that must be completed to deliver the project deliverables. After this, the schedule and budget for the project are determined. Various methods for controlling a project are also discussed, for example, procedures to follow in order to keep the project within budget, on schedule, and within the tolerances established by the project board.
A permanent owner is assigned to all projects after the product has been delivered. A project might result in providing a service, such as a training course. In addition to describing the product, product descriptions describe its purpose, composition, format, quality criteria, and any other items relevant to its development. A detailed product description will make the project team better prepared to successfully complete the project on the first attempt.
Detailed information on the current status of the product can be found in the product status account. Typical uses include communicating production information, testing results, and current cost status.
In the project brief, it is explained what the project is intended to accomplish. A business case consists of information such as the project objectives, project scope and scope exclusions, tolerable, and any other relevant data. Starting Up a Project is the first step in the project planning process, so this document is produced first. In order for the project to be successful, the parent organization uses this document.
PRINCE2's PID is probably its most important document. Project planning is contained in this document. These components include information regarding the project's stages, schedule, budget, and quality criteria, as well as anything else necessary to its success. It provides a snapshot of the current project status and is updated regularly. A roadmap is displayed at all times, outlining the current project status. The PID is, however, preserved for purposes of evaluating the overall performance of the project. Among its parts are:
A primary component of any project is its description of the products or services it will deliver. There are times when everyone knows what is being produced, but in many situations, the product description is an essential aspect that needs to be reviewed regularly to continue to maintain focus on the end goal. A detailed discussion and analysis of the quality expectations are imperative for ensuring a quality final product. To avoid changing goalposts mid-project, the acceptability criteria for the product need to be discussed and stated in the product description. Enroll in project management training and certification programs and start writing captivating product descriptions.
Quality standards are discussed in this document as well as how they will be reached and measured. Almost every project is concerned with quality. Clients and customers expect a certain level of quality from service providers, even if they don't express it. In many cases, the expectations of the project team and the customer differ when it comes to quality - usually, it's the customer who expects a Range Rover when the project team expected to deliver a BMW.
A Quality Register keeps track of quality activities in order to ensure adequate project quality. Quality control (QC) is an important component of many projects, as it measures how much of a widget is out of specification at the tail end of the production process.
This approach identifies the risks and the risk management activities to be performed. The procedure for identifying and analyzing risks, probability, severity indices, and risk responses is described in detail. Organizational risk tolerances are analyzed and responsibilities for risk management plans are identified.
There is a Risk Register that lists the risks that may influence the project's success. There are two primary factors that determine risk probability and severity. A risk response plan is developed to address the most important risks when they occur. Each phase of the project is evaluated by the project management team in the PID, or at the end of each stage.
Project tasks are summarized into work packages. A project task can be categorized into different work packages. The team manager is responsible for controlling work packages, according to the project manager. A management stage is a group of work packages. To ensure the work packages do not deviate from the project plan, work packages must be measured against tolerances, for example, scope and budget. All issues occurring must be recorded in the Issue Log, and if necessary, a Project Board Issue Report should be sent out.
Learn PMP and advance your project management skills with our comprehensive online course. Our expert instructors and study material will prepare you for success on the exam and help you achieve your career goals. Enroll now to take the next step towards mastery in project management.
Choose the documents your project needs based on its needs. You can use this guide only for guidance. Handle your project well by using the appropriate paperwork. Keep your focus on what you want, not what you need. You can use the above list as a guide for what most projects require. Know more about KnowledgeHut PRINCE2 certification course.
A. It is necessary to rethink the date and detail phases of the project for the initial plan for project initiation documentation. The documents required to initiate a project are -
A. PRINCE2 provides several important project planning functions through the project initiation document (PID). These documents help stakeholders get on board and engage project teams which provides crucial context.
A. Here are seven simple steps to creating a project initiation document
Name | Date | Fee | Know more |
---|